October 22, 2026
"We didn't have any parks to go to in our neighborhood." Diane King, a retired city staffer, said that at the North Park groundbreaking on September 3, as the Boca Raton Tribune reported. She added that she liked the idea of kids someday walking five blocks to a park.
That "someday" is doing a lot of work. North Park is the Greater Boca Raton Beach & Park District's 212-acre park on the old golf course in Boca Teeca, which the District bought in 2018. It's coming in a different order than most people would guess. The first big piece to open, on November 18, is a members-and-day-pass racquet club. The free walking trails, dog park and playground are under construction with no finish date. The skatepark has its approvals but no start date. And the west side is back to a blank page. If you live in Boca Teeca, or you drive past the site on Federal Highway or I-95, here's what you can actually use and when.
The only part of North Park open to the public right now is the Traffic Garden, west of NW 2nd Avenue. The District describes painted "streets," child-sized traffic signs, seating, restrooms, shade and parking right next to it. It had a soft opening in August 2025. That means North Park spent more than a year with one usable feature, and that feature was designed for children learning to ride.
The District has used it for programs like a Kids Safety Fair on February 18, 2026. That event was free and open to ages 5 to 10, with adult supervision, bring-your-own bikes or push scooters, and no electric vehicles. Those were rules for one event. For everyday hours, check with the District before you load up the bikes.
The second piece of North Park, and by far the largest so far, is Boca Paddle by CityPickle. It's a public-private partnership with the Beach & Park District, and it opens November 18. TAPinto Boca Raton reported these details from the club's announcement:
This is the part of North Park you'll pay to use. The Boca Post went through the club's FAQ and found that a membership doesn't include court time. Court rentals, open play, clinics and leagues are billed separately at member rates. Without a membership, you can buy a day pass as often as you like. The 2026 price is $35 for Boca Raton residents with proof of residence and $40 for everyone else. Each person can also visit free as a member's guest once every 60 days. The Boca Post also noted that the District hasn't disclosed the financial terms with the operator, including whether it collects rent or a share of revenue.
The one part of the building that's free to walk into is the restaurant. Farmer's Kitchen by Farmer's Table is a full-service restaurant and bar led by Chef Michael Schenk, and it will be open to the public without a membership or day pass. Until the trails open, a meal there overlooking the courts is the easiest way for anyone to spend an evening at North Park without paying for court time.
If you're curious before opening day, the Boca Raton Tribune reported that the club is offering public hard-hat tours by appointment.
Most of what people picture when they hear "212-acre public park" is on the east side, and that work only started in September. The District broke ground on the 70-acre east side on September 3, 2026. Butters Construction & Development, the company that built Boca Paddle, holds the contract. The plan calls for more than five miles of walking and riding trails, a dog park, a playground, exercise equipment along the trails and more than 1,000 native trees.
The District hasn't announced a cost or a completion date for this phase. So the free, everyday part of the park, the place to walk a dog or push a stroller, comes after the paid club, and nobody has said how long after.
| North Park piece | Status as of late October 2026 | Cost to use |
|---|---|---|
| Traffic Garden | Open since its August 2025 soft opening | Not posted for everyday use |
| Boca Paddle by CityPickle | Opens November 18, 2026 | $35 resident day pass, $40 nonresident, court time extra |
| Farmer's Kitchen by Farmer's Table | Opens with the club | No pass required to dine |
| East side trails, dog park, playground | Under construction since September 3, 2026 | Public park; no completion date announced |
| Skatepark and pump track | Design and city approvals done; no construction date | Not announced |
| West side | No approved plan | Not applicable |
After the east side, the skatepark is the next piece in line. Its approvals are finished. The District's commissioners approved a 42,000-square-foot design on January 20, 2026. It includes a pump track, a snake run, a street course and bowls. On September 3, the same day as the groundbreaking, Boca Raton's Planning and Zoning Board approved the skatepark and pump track 7–0. The Boca Post described that as the final city land-use vote, and said no construction schedule had been set.
The approval came after public debate. The Boca Post reported that representatives of Boca Teeca condominiums asked to delay or move the skatepark and requested noise and traffic studies. Six condo boards filed resolutions favoring golf, a community center and green space over development they considered incompatible. Golf advocates also objected to the location. The board approved it anyway. That settles the skatepark's location but not its timing.
The east side is moving. The west side isn't, and the past year shows how hard it has been to settle. In October 2025, the District's shortlist of west-side ideas included a surf park, an indoor fieldhouse and golf amenities, along with a Boys & Girls Club. In November 2025, the Boca Raton Tribune reported, the District rejected every west-side proposal except the Boys & Girls Club concept. It then called for a new community-needs assessment with the City and a revised request for proposals.
Then the Boys & Girls Club deal ended too. On August 17, 2026, three of the District's five commissioners voted to stop negotiating with the club. The Boca Raton Tribune reported that the open issues included the term "concessionaire," the building's undecided size, and a fundraising, design and construction timeline that could run as long as 10 years. Before the meeting ended, Commissioner Steve Engel raised "another location for a fieldhouse" on the site, and Chairman Robert Rollins replied, "The seed is planted."
You may have seen opening dates attached to earlier west-side plans in Boca Magazine's coverage, such as a fieldhouse in August 2027 or surf park phases in 2028 and 2030. Those dates came from vendor proposals the District later rejected. They aren't on any approved schedule. The District's own project page calls North Park a conceptual plan focused on trails, biking and green space, with a fieldhouse, a skatepark and aquatic facilities listed as possible future features.
So for the rest of 2026, North Park is mostly a destination for people who play pickleball or padel, plus a Traffic Garden for families with young riders. The park King described at the groundbreaking, the one kids can walk to, depends on an east-side phase that hasn't been dated yet.
Here's what that means this fall:
If you live near Boca Teeca and wonder what North Park's slow rollout means for your street, or you're comparing pockets of Boca that are close to new parks, I'm glad to talk it through over coffee, or maybe lunch at Farmer's Kitchen once it opens. Reach out to Rachel Hutchings to schedule a free consultation.